Coordination between disciplines
What coordination is not
Section titled “What coordination is not”Everyone sending their drawings to the others. That still leaves the possibilities that:
- nobody looks at them,
- they are working from different versions,
- and two disciplines are using the same space.
What coordination is
Section titled “What coordination is”Shared base data
Section titled “Shared base data”Everyone works from the same architectural base, with the same version number. That sounds trivial, and a significant share of mistakes comes from it anyway.
Regular meetings
Section titled “Regular meetings”Not when there is a problem, but to a schedule. Short, regular sessions are worth more than rare, long ones.
Recorded decisions
Section titled “Recorded decisions”What has been decided has to be written down — who it is for, from when it applies.
Clash detection
Section titled “Clash detection”With model-based working this can be partly automated. Clash detection.
Change control
Section titled “Change control”The most important element. If something changes, everyone affected has to know.
Why it is critical for a prefabricated structure
Section titled “Why it is critical for a prefabricated structure”Because the structure arrives manufactured. Changing drawings that were closed before manufacture means the member made becomes scrap.
So coordination between disciplines has to close before manufacture — not during construction.
That is one of the technology’s greatest demands for discipline, and the reason well-coordinated projects are faster here while badly coordinated ones are more expensive than with traditional technology.
The practical sequence
Section titled “The practical sequence”- Fix the architectural base.
- Structural concept and spans.
- Services concept and routes.
- Resolve the clashes.
- Finalise the build-ups.
- Structural detailed design.
- Shop drawings.
Every step back in that sequence costs time and money — and it is cheapest when it happens at the top of the list.
The point
Section titled “The point”Coordination is not administration but the prevention of mistakes. For a prefabricated structure it is the difference between a fast project and an expensive one.