Erection sequence
The state during erection
Section titled “The state during erection”The stability of the finished structure comes from the bracing, the lining and the connections together. During erection some of them are still missing.
So the state during erection is a separate load case:
- the frame stands with less restraint,
- the wind already acts in full,
- and lifting and handling load it too.
Temporary bracing
Section titled “Temporary bracing”Not optional. Where the permanent bracing is not yet complete, temporary bracing is needed — and it can only be removed as erection progresses.
That is especially true for:
- trusses, which are unstable out of plane,
- tall wall panels before lining,
- long, narrow parts of the building.
The typical sequence
Section titled “The typical sequence”- Survey and level the foundation. Setting out and foundation tolerances.
- Place the bottom tracks, with damp-proofing.
- Stand the wall panels, with temporary bracing.
- Install the hold-downs and the permanent bracing.
- The floor structure.
- The next storey, the same way.
- The roof structure.
- The linings that provide the permanent bracing.
At every step there is a point at which the structure is not yet final — there the temporary solution holds it.
What the design has to contain
Section titled “What the design has to contain”- the logic of the erection sequence,
- the position and method of the temporary bracing where it is critical,
- the lifting points for a panelised structure,
- the manufacturing and delivery sequence, so the members arrive in erection order.
That last detail is often overlooked, yet on a tight site it decides whether things have to be double-handled.
The timing of inspection
Section titled “The timing of inspection”Erection is the time when the structure is still visible. The bracing, the screw fixing and the anchorage can be checked then — not once the lining is on. Inspection points.
The point
Section titled “The point”The frame is weaker during erection than when finished. Temporary bracing is not over-caution but part of the structure until the permanent bracing is done.