Load testing and verification
Why verification is needed
Section titled “Why verification is needed”Because the properties of the ground vary from point to point, while the design works with characteristic values. The actual capacity emerges at the place of installation.
That is the nature of geotechnics: here the construction is also a measurement.
The load test
Section titled “The load test”What it does
Section titled “What it does”The element is loaded with a known, gradually increased load and the movement is measured. The result is a load–displacement curve from which the capacity can be established.
When it is warranted
Section titled “When it is warranted”- where the ground conditions are uncertain,
- where the capacity is critical in the design,
- where many identical elements are installed and the result can be extended to the whole series,
- where the tension capacity governs.
What it gives
Section titled “What it gives”Far stronger evidence than calculation, because it measures the behaviour of the real ground and the real element.
Installation torque
Section titled “Installation torque”With ground screws the torque measured during installation correlates with the expected capacity. That is valuable because:
- it is available for every element, not only the one load tested,
- it immediately signals where the ground differs from expectations,
- it can be recorded, so it can be retrieved afterwards.
If an element goes down at a lower torque than expected, that is a warning: the ground is weaker there.
What has to be recorded
Section titled “What has to be recorded”- the position and identifier of the elements,
- the installation depth,
- the torque measured,
- the results of the load tests,
- the deviations and the action taken.
This is part of the foundation documentation, and irreplaceable at a later extension or in a dispute. Handover documentation.
The observational method
Section titled “The observational method”In complex cases the geotechnical standard allows the design to be based on measurements during construction, with thresholds and an intervention plan set in advance. That is not improvisation but a regulated procedure.
The point
Section titled “The point”With the ground, the evidence is the measurement. One load test is worth more than any detailed calculation — and the installation data gives the rest for free.