Surveying an existing building

For three reasons:

  1. It may not have been built the way the drawing shows.
  2. Later alterations may have been made, undocumented.
  3. The condition — cracks, damp, corrosion — is not revealed by a drawing.

So the old drawing is a starting point, not evidence.

Exact dimensions, floor levels, openings, grid lines. The basis of all further design.

What carries load: walls, columns, type of floors, spans, directions. It determines where load can be applied.

Type of masonry, floor construction, condition of existing steel or timber members.

Critical for an extension or a rooftop addition: what foundation there is, how deep, with how much reserve capacity. This often requires trial pits.

Existing services and electrical installation

Section titled “Existing services and electrical installation”

If the extension connects to them.

Here the reserve capacity of the existing structure decides: how much additional load the foundations and the vertical structure can take.

This is the situation where light gauge steel is at its strongest: the low self-weight is often precisely what the existing building can still take. Rooftop additions.

But even for that you have to know what the reserve is — you cannot build on an assumption.

  • topographic and building survey for the geometry,
  • non-destructive testing where possible,
  • targeted opening up where it is unavoidable — foundations, floor construction,
  • material testing where the capacity is in question,
  • and recording the survey, because it becomes the basis of the design.

However thorough the survey, uncertainty always remains with an existing building. So the contract has to state what happens if something unexpected emerges during the strip-out.

For an existing building the survey is the most important input to the design. What is not surveyed is an assumption — and a design built on assumptions collapses at the strip-out.