Site-erected frame, panel, module
The three methods
Section titled “The three methods”Frame erected on site
Section titled “Frame erected on site”Production delivers cut-to-size, marked members, and the frame is assembled on site. Little space needed, simple transport, flexibility to site conditions.
In exchange, site work takes longer and quality depends more on the installers and the weather.
Panelised production
Section titled “Panelised production”Wall panels — and often floor and roof elements — are assembled in the plant: frame, sometimes lining, insulation, sometimes even windows. On site the panels are put together.
Shorter site time, better controlled quality, in exchange for greater logistical demand and more constrained design.
Modular (volumetric)
Section titled “Modular (volumetric)”Complete three-dimensional units are finished in the plant, often with linings, services and sometimes furniture. On site they are connected together.
The shortest site time and the highest factory quality, but serious transport and lifting requirements and the most constrained geometry.
What decides between them
Section titled “What decides between them”- Site conditions: whether there is room for craneage, storage and access.
- Transport distance: moving large elements is expensive.
- Project size and repetition: prefabrication pays off better in series.
- Time pressure: where site time is critical, more prefabrication wins.
- Manufacturing capacity: whether there is an assembly plant or only profile production.
The legal consequence not to forget
Section titled “The legal consequence not to forget”In Hungarian regulation it matters whether the building is assembled from prefabricated panels or whether a frame erected on site is clad. The two are different legal categories requiring different verification.
This depends on the method of construction, not on the production line: the same machine can produce panels in a plant and cut members for site assembly. The concept of lightweight technology.
The effect on design
Section titled “The effect on design”Panelisation is not a decision to take afterwards. If we think in panels, panel sizes, joints, lifting points and transportability have to be fixed during design. Panel size and transport.
The point
Section titled “The point”The degree of prefabrication is a strategic decision: it trades site time for logistics and design constraint — and on the way it can change the legal category as well.