The three legs
Section titled “The three legs”The requirement is not a single number but three conditions together:
1. Low energy demand
Section titled “1. Low energy demand”Good insulation, low heat loss, good airtightness, thermal-bridge-free junctions.
2. Efficient building services
Section titled “2. Efficient building services”Low-loss heating, domestic hot water and ventilation — with heat recovery where it is warranted.
3. Renewable energy
Section titled “3. Renewable energy”A significant part of the demand has to be covered from renewable sources.
If any one is missing, the requirement is not met — however good the structure is.
Where light gauge steel has the advantage
Section titled “Where light gauge steel has the advantage”Insulation thickness grows freely
Section titled “Insulation thickness grows freely”Increasing the insulation in a framed build-up does not bring a disproportionate wall thickness. For the same thermal value the whole wall can be much narrower than in traditional construction.
Airtightness is achievable
Section titled “Airtightness is achievable”The continuous membrane layer and the service cavity are a good starting point. Service cavity.
Fast response
Section titled “Fast response”Because of the low thermal storage mass the building heats up quickly, which suits control.
What to watch
Section titled “What to watch”Thermal bridges
Section titled “Thermal bridges”Because of the steel frame this is the most important item. A badly handled thermal bridge takes away the advantage in the calculation and in reality alike. Ways of breaking a thermal bridge.
Summer overheating
Section titled “Summer overheating”A well-insulated, airtight building “holds” the heat in summer too. Shading and ventilation cannot be dropped. Summer overheating.
Coordination between services and structure
Section titled “Coordination between services and structure”The service routes go into the build-up — so coordination between disciplines has to start early.
The calculation
Section titled “The calculation”Compliance is demonstrated by an energy calculation, following the methodology of the decree in force. Energy performance requirements.
The point