Site data, survey and setting out
What a design needs to start
Section titled “What a design needs to start”Title and map data
Section titled “Title and map data”Title deed and map extract: the exact boundaries of the plot, the encumbrances, the easements.
Topographic survey
Section titled “Topographic survey”The levels of the ground, existing objects, trees, retaining walls, the position of neighbouring buildings. This gives the datum for the design.
Without an accurate survey the ground connection, the level of the entrances and the drainage are all uncertain.
Utility data
Section titled “Utility data”Where the services are, with what capacity, on what conditions they can be connected. Utility connections.
Planning data
Section titled “Planning data”The relevant provisions of the local building code, any protected status. Local building code.
Ground investigation
Section titled “Ground investigation”Where warranted — and for the cost of the foundations that is nearly always. Ground investigation report.
For an existing building
Section titled “For an existing building”Add a survey of the existing structure: geometry, structural system, condition, capacity. Surveying an existing building.
Why to start here
Section titled “Why to start here”Feasibility is decided here
Section titled “Feasibility is decided here”The plot may not allow what the client wants. Better to find that out in the first week.
The cost estimate rests on it
Section titled “The cost estimate rests on it”Foundations, earthworks, utility connections — large items, all dependent on the site data.
The design work is not wasted
Section titled “The design work is not wasted”A design produced without a survey often has to be started again once the real data is known.
The accuracy question
Section titled “The accuracy question”For a prefabricated structure the setting out and the vertical accuracy matter particularly, because manufactured members do not adapt. Setting out and foundation tolerances.
So the survey work does not end with the design: it is needed during construction too.
The point
Section titled “The point”Gathering data is the cheapest stage of the design and the one that reduces the most risk. Save on it and you pay in the construction.