The ground investigation report
What it contains
Section titled “What it contains”A ground investigation report typically gives:
- the stratigraphy: which layers follow one another and to what depth,
- the physical and mechanical properties of the layers,
- the water table and its likely fluctuation,
- findings on bearing capacity and settlement,
- a recommendation on the foundation type and depth,
- a warning about particular risks: swelling clay, made ground, organic layers, voids.
Why it cannot be skipped
Section titled “Why it cannot be skipped”The ground is not visible
Section titled “The ground is not visible”The surface of a plot tells you nothing about what is beneath. A layer of made ground or the remains of an earlier building does not show at the surface.
The neighbour’s experience is not enough
Section titled “The neighbour’s experience is not enough”Ground conditions can change within a few metres.
The mistake is expensive
Section titled “The mistake is expensive”A foundation mistake is hard to repair afterwards: settlement, cracking, structural damage. The cost of an investigation is negligible against that.
What to view differently for a light structure
Section titled “What to view differently for a light structure”Lower load, but not zero
Section titled “Lower load, but not zero”Because of the low pressure, more ground types are suitable than for a heavy building. That holds even where the ground is otherwise weak — which is why a simpler foundation can often be designed.
Uplift is a new question
Section titled “Uplift is a new question”The ground also has to take tension where the anchorage goes into it. That matters especially with ground screws.
Differential settlement is more of a problem
Section titled “Differential settlement is more of a problem”An accurate, stiff frame tolerates differential movement less well than a masonry structure, which “absorbs” it in cracks. So limiting differential settlement matters.
The geotechnical category
Section titled “The geotechnical category”The depth of investigation is not always the same: it follows the complexity of the task. A simple, small building on known ground calls for less investigation than a complex structure on difficult ground. Geotechnical categories.
When to commission it
Section titled “When to commission it”Before buying the plot, if possible — or at least at the start of the design. The foundation type is one of the largest cost items, and the ground makes that decision, not the designer.
The point
Section titled “The point”A ground investigation is not a cost but risk reduction. Either you get to know the ground in advance or you get to know it during construction — and that is more expensive.