Because everyone is at the end by then, and the paperwork is the least visible part of the project. Yet it is what remains of it for the building’s remaining decades.

What was actually built — not what was designed. Where there was a deviation, it has to be recorded here.

Declarations of performance, tied to the place of installation. An unsorted heap of PDFs is formally delivery and practically useless. How to read a declaration of performance.

Airtightness test, electrical tests, pressure tests, commissioning records, and whatever else was produced on the project.

The fire solutions, their verification, the register of the seals. On a larger building this is drawn together in the fire technical compliance manual. Fire documentation.

What has to be done and how often. It is also a condition of enforcing warranty claims.

What matters particularly for a light gauge steel house

Section titled “What matters particularly for a light gauge steel house”

Photographs and entries showing the state before the lining went on. That is what tells you, at a later alteration, where you can drill, where the bracing is and where the vapour control layer runs.

“Two layers of plasterboard” is not enough: the type and thickness matter, because the fire and acoustic performance rests on them.

What can be hung where on the wall — the occupants’ most frequent question. What you can hang on the wall.

  • Warranty claims are hard to enforce.
  • At a sale the buyer and the bank find a gap.
  • At an alteration the designer has to survey what should have been documented.
  • After an insurance event the insurer asks questions.

On the first day of construction. Start in the week of handover and it cannot be assembled — the concealed work is concealed by then.

The handover documentation is not the end of the project but the start of operating the building. What is not handed over here, somebody pays for again later.